As we start 2011

The contractor beat the winter to

  • Final pour of N Huntington and Huntington (on the south side)
  • Opened the intersection of Huntingtons and Bainbridge Rd, with a 4 way stop
  • Laid a temp road with portable concrete barriers (PCB) near the power lines (Culvert 10)

The contractor also

  • Rebuilt Culvert 13 between Windy Hill and Creekside
  • Worked on underground utilities in Phase 1 East and Phase 2

Now in early March the contractor has announced they will start building the temp road east of Huntington.