The contractor beat the winter to
- Final pour of N Huntington and Huntington (on the south side)
- Opened the intersection of Huntingtons and Bainbridge Rd, with a 4 way stop
- Laid a temp road with portable concrete barriers (PCB) near the power lines (Culvert 10)
The contractor also
- Rebuilt Culvert 13 between Windy Hill and Creekside
- Worked on underground utilities in Phase 1 East and Phase 2
Now in early March the contractor has announced they will start building the temp road east of Huntington.